Challenge
Needed to design a lean production system capable of ramping immediately and exponentially
Supply chain was very constrained by the pandemic requiring flexibility and creativity
Filling vials with solution at a high volume required automation
The system consisted of 300 individual sub-assemblies. It proved very difficult to find an FDA certified manufacturer with both electronics and fluidics expertise.
Outcomes
Within 4 days Evolve had a production line with semi-automated processing equipment
Within 10 days the production output was 10000 covid test kits per day
Within 60 days the production output was 50000 covid test kits per day
Evolve’s Value Proposition
Demonstrated ability to bring up a high volume lean manufacturing line in record time
Expert in designing tooling and setting up automation to handle a seamless ramp
Evolve’s systems are designed to respond to quickly changing conditions while maintaining the strictest FDA standards